| S No | Project | Voltage (kV) |
Line Length (km) | Capacity (MW) | Appn No | Appn Date | Promoter |
Address | Start Point |
End Point |
Remarks |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Upper Karnali Hydroelectric Project 400 kV Transmission Line | 400 | 900 | 6091 | 2072-03-20 | Karnali Transmission Company Pvt. Ltd. | Chakupat-10, Lalitpur, P.O. Box: 148, Tel: 5540718, Fax: 5540659 | Bhairabsthan, Accham | Brahmadev, Kanchanpur | Survey Lic No: 119 Date: 2067-03-23 | |
| 2 | Upper Marsyangdi-2 Hydroelectric Project 400 kV Transmission Line | 400 | 600 | 6093 | 2072-03-21 | Marsyangdi Transmission Company Pvt Ltd | Chakupat-10, Lalitpur, P.O. Box: 148, Tel: 5540718, Fax: 5540660 | Taghring, Lamjung | Bodabar, Rupandehi | Survey Lic No: 120 Date: 2067-03-23 | |
| 3 | Super Trishuli HP 220kV TR Line | 220 | 30 | 100 | 1538 | 2076-05-20 | Blue Energy P Ltd | Darbar Marg Kathmandu, POB 9609, Ph 4233516 | Switchyard | Bharatpur substation | Survey Lic No: 209 Date: 2071-05-26 Er.Vijay |
| 4 | Transmission line for Betan Karnali Construction Power | 33 | 30 | 6 | 1144 | 2079-05-07 | Betan Karnali Sanchay Karta Hydropower Co. Ltd. | Darbarmarg,Kathmandu | Sugarkhal Substation(Surkhet Aachham ) | Betan Karnali Project Site(Surkhet) | Survey Lic No: 439 Date: 2076-09-04 |
| 5 | Khare Khola Hydropower Project | 132 | 9 | 24.1 | 3583 | 2079-09-06 | Consoriun Power Developers Pvt.Ltd. | 316 Baburam Acharya Sadak ,Sinamangal -9 Kathmandu | Switchyard of Hydropower Project (Dolkha | Singati NEA Substation(Dolakha) | Survey Lic No: 446 Date: 2076-09-20 |
| 6 | Dudhkoshi Storage Transmission Line Project | 400 | 90.9 | 600 | 6301 | 2081-01-31 | Nepal Electricity Authority | Main office,Darbarmarg,Kathmandu | Switchyard of Dudhkoshi Storage HPP | Dhalkebar NEA Substation | Survey Lic No: 394 Date: 2076-02-03 |
| 7 | Mathillo Tadi HPP- Samundratar 33 kV Transmission Line Project | 33 | 7 | 11 | 7244 | 2081-03-04 | Suryakunda Hydroelectric Limited | Trade Tower, Thapathali, Kathmandu | switchyard of the project | NEA Samundratar S/S | Survey Lic No: 651 Date: 2081-04-16 |
| 8 | Inaruwa-Anarmani 400 kV Transmission Line Project | 400 | 91 | 2600 | 1964 | 2081-06-11 | Nepal Electricity Authority | Durbar Marg, Kathmandu 01-4153007 | NEA Inaruwa S/S | Proposed New Anarmani S/S | Survey Lic No: 548 Date: 2079-02-06 |
| 9 | Trishuli 3B- Ratamate 220 kV Transmission Line Project | 220 | 23.5 | 1234 | 3422 | 2081-08-13 | Nepal Electricity Authority | Durbarmarg Kathmandu | Trishuli 3B Hub S/S | Ratamate S/S | Survey Lic No: 652 Date: 2081-04-18 |
| 10 | Tingla Hub to Dhalkebar | 400 | 155 | 2500 | 4166 | 2081-09-12 | Nepal Electricity Authority | Main office,Darbarmarg,Kathmandu | Tingla Hub(Solukhumbu),Likhu,New Khimti | Dhalkebar NEA Substation (Dhanusha) | Survey Lic No: 442 Date: 2076-09-15 |
| 11 | Lamosanghu Kavre Ramechap | 132 | 36 | 238 | 4167 | 2081-09-12 | Nepal Electricity Authority | Main office,Darbarmarg,Kathmandu | Lamosanghu(Sindhupalchowk) | Proposed New Substation at Boundry of Ra | Survey Lic No: 443 Date: 2076-09-16 |
| 12 | Phukot Karnali PROR HEP 400 KV TL | 400 | 2.5 | 480 | 8289 | 2082-01-28 | Vidhyut Utpadan CompNy Limited | BPC Building, Rudramatimarg Kathmandu, 01-4788680, info@vucl.org | Project Powerhouse | Phukot Substation | Survey Lic No: 454 Date: 2077-01-30 |
| 13 | Kalinchowk Small HPP 33kV Transmission Line Project | 33 | 12 | 3 | 9360 | 2082-02-26 | Himalayan Energy Pvt.Ltd | New Baneshwor | Respective Switchyard of the project | Singati s/s | Survey Lic No: 692 Date: 2081-11-01 |
| 14 | Balaju Singhdurbar (K3) Under Ground Transmission Line Project | 132 | 12 | 350 | 9498 | 2082-02-29 | Nepal Electricity Authority | Durbar Marg, Kathmandu 01-4153007 | Balaju S/S | Singhdurbar K3 S/S | Survey Lic No: 604 Date: 2080-03-13;Double ckt |
| 15 | Auraha Simara 132 kV Transmission Line Project | 132 | 7 | 200 | 606 | 2082-04-15 | Nepal Electricity Authority | Durbar Marg, Kathmandu 01-4153007 | Between T.N. 25&26 of Pathalaiya Parwani | Simara S/S | Survey Lic No: 584 Date: 2079-11-12:Double ckt |
| 16 | Upper Arun Hydro Electric 400 kV Transmission Line | 400 | 6.5 | 1066 | 866 | 2082-04-26 | Upper Arun Hydro Electric Limited | Durbarmarg Kathmandu; 01-415322, Fax 01-4153040, E-mail: upperarun@nea.org.np | UAHE Plant Switchyard | Haitar S/S | Survey Lic No: 460 Date: 2077-04-28;Double ckt |
| 17 | Upper Irkhuwa khola HPP 33kV Transmission Line Project | 33 | 10 | 30.024 | 1217 | 2082-05-05 | Aarati Power Company Limited | Gahanapokhari, KTM-05; 01-4419321 | Switchyard of Project | NEA Sitalpati S/S | Survey Lic No: 543 Date: 2079-01-11;single/Double ckt |
| 18 | Kapilbastu Solar Power 33kV Transmission Line Project | 33 | 9 | 30 | 1650 | 2082-05-18 | Prime Power Limited | Tripureshwor-11,kathmandu | Respective Switchyard of the project | Chanauta s/s | Survey Lic No: 707 Date: 2082-02-11 |
| 19 | Chameliya (Chhetigad) HPP Transmission Line | 132 | 22 | 85 | 1737 | 2082-05-20 | Grid Nepal Company Pvt. Ltd. | Pandol Marg, Khursanitar Lazimpat, Kathmandu-03; | Switchyard of Project | NEA Balanch S/S | Survey Lic No: 468 Date: 2077-05-24;Double Ckt |
| 20 | Sitalpati-Inaruwa 400 kV Transmission Line Project | 400 | 95 | 4400 | 2167 | 2082-06-10 | Nepal Electricity Authority | Durbar Marg Kathmandu | NEA Sitalpati S/S | NEA Inaruwa S/S | Survey Lic No: 506 Date: 2078-06-15;Double ckt |
| 21 | Arun Hub (Sitalpati) -Tingla-Dudhkoshi 400 kV Transmission Line Project | 400 | 110 | 4400 | 2168 | 2082-06-10 | Nepal Electricity Authority | Durbar Marg Kathmandu | Sitalpati S/S | Proposed Dudhkoshi (khotang)S/S | Survey Lic No: 507 Date: 2078-06-24 |
| 22 | Ikuwa Khola HPP Transmission Line Project | 132 | 3 | 30 | 2626 | 2082-07-09 | Upper Arun Hudro-Electric Limited | Durbar Marg, Kathmandu. 01-4117163/54/65; upperarun@nea.org.np | Switch yard of Project | Arun Hub Substation Haitar | Survey Lic No: 477 Date: 2077-07-17 |